Every central government infrastructure project (₹150 crore and above) as an open ticket — how long it has run, how late it is, what it costs now. Each ticket is automatically truth-checked by AI against live public reporting.

First time here? Beacon turns government project records into open tickets — delays, costs and AI truth-checks, all sourced. How this works →
Loading map…

Projects in Uttar Pradesh

177 open · 123 late · ₹472,008 crore. MP report cards in Uttar Pradesh.

  1. Six Laning of Varanasi to Aurangabad from km. 786.00 to km. 978.40 of Old NH-2 — 147 months late
  2. Varanasi Gorakhpur Section Packege IV from km. 149.540 to km. 215.160 Mau Gorakhpur — 78 months late
  3. Saryu Nahar CADWM Project — 75 months late
  4. Madhya Ganga canal Phase-II — 72 months late
  5. 4L of Haridwar-Nagina section from km. 0.00 to km. 71.614 of NH-74 — 69 months late
  6. Ghatampur Thermal Power Plant 3 X 660 MW — 64 months late
  7. Kandla Gorakhpur LPG Pipeline — 54 months late
  8. Varanasi Ring Road Pkg-II connecting Sandaha Village km 11.70 / NH-29 with Revasa Village km 818.80 / NH-2 — 52 months late
  9. 502 Aspirational District Scheme in Four states - Bihar, Madhya Pradesh, Rajastha and Uttar Pradesh — 51 months late
  10. Balance work of Construction of Ring Road for Raebareli City on eastern side of NH 24B Phase-1 on EPC mode. — 50 months late
  11. Jhansi - Bina Third Railway Line [153 Km] — 48 months late
  12. Aligarh-Kanpur Pkg I [Aligarh-Bhadwas] — 46 months late
  13. Western Dedicated Freight Corridor — 45 months late
  14. Banaras Hindu University [ Kayakalp of Institute of Medical Sciences] — 42 months late
  15. Agra Metro Rail Project — 37 months late
  16. BINA KAKRI AMALGAMATION EXPANS — 36 months late
  17. Mobile connectivity in Left Wing Extremism [LWE] affected areas-Phase2 — 36 months late
  18. Rehabilitation & Upgradation of NH-731A from Km.0.00 to Km.35.00 to 2-lane with paved shoulder under EPC mode — 36 months late
  19. Bijnor-Kotawali — 35 months late
  20. Jhansi Water Supply Infrastructure Phase-II Project — 34 months late
  21. Kanpur Metro Rail Project — 34 months late
  22. Construction of 6-lane bridge on Ganga on NH-96 and its approaches in Phaphamau Allahabad on EPC mode — 31 months late
  23. 6L access-controlled highway from Ganeshpur tonear Mohand of Ganeshpur Dehradun section from Km.0 to Km.8.3 of NH-72A Package-1 — 30 months late
  24. DL/UP Border - EPE Crossing Pkg-02 — 29 months late
  25. Pollution Abatement Works for River Kali Meerut under Meerut Municipality Interception & Diversion with STP — 29 months late