The public ticket board

Every central government infrastructure project (₹150 crore and above) as an open ticket — how long it has run, how late it is, what it costs now. Each ticket is automatically truth-checked by AI against live public reporting.

First time here? Beacon turns government project records into open tickets — delays, costs and AI truth-checks, all sourced. How this works →
Loading map…

Projects in Telangana

89 open · 72 late · ₹105,464 crore. MP report cards in Telangana.

  1. Rehabilitation and upgradation of NH-221 from km 121/0 to 165/0 Rudrampur to Bhadrachalam section to two lane with paved shoulder under NHDPIV in the state of Telangana through EPC mode — 110 months late
  2. Widening to two/four lane with paved shoulder from Km.180.600 to Km.223.000 of NH-63 on Nizamabad-Jagadalpur road on EPC mode under NHO in the state of Telangana. — 89 months late
  3. Widening to 2/4 Lane with paved shoulders from Km 182.120 to Km 227.600 of NH 167 on Haggari-Jadcherla Road on EPC mode under NHO in the state of Telangana — 85 months late
  4. Indiramma Flood Flow Canal Project — 84 months late
  5. widening to two lane with Paved shoulders from Km.0/970 to Km.40/410 of Jangaon - Thirumal giriof NH- 365B in the state of Telanganaon EPC mode under NHO Annual Plan 2016-17 — 82 months late
  6. Widening to Two with Paved shoulders from Km 59.500 to Km 132.033 of Manneguda- Ravunapally section of NH-163 Erstwhile SH-4 in the State of Telangana on EPC mode under NH O Annual Plan 2016-17 — 79 months late
  7. Widening to Two Lane with Paved Shoulders from Km 67.000 to Km 114.425 of Kalwakurthy- Mallapally Section of NH 167 Erstwhile section of SH 18 in the State of Telangana on EPC mode under NH O Annual Plan 2016-17 — 79 months late
  8. Rehabilitation and upgradation of NH-167 from design km 157.707 to 187.723 design length 30.016 km to two lane with paved shoulders of Alinagar-Miryalaguda Sec on EPC mode in the state of Telangana — 79 months late
  9. Rehabilitation and upgradation to two lane with paved shoulders from Km 0/000 to 72/6 of NH-365 Nakrekal to Tanamcherla section under NHDP IV in the state of Telangana under EPC mode — 78 months late
  10. Rehabiitation and upgradation from km 121/000 to 154/000 Nakrekal to Mallampally section of NH-365 to 2 lane with paved shoulders in the state of Telangana in the EPC mode — 77 months late
  11. Rajiv Bhima Lift Irrigation Scheme — 75 months late
  12. Construction of six lane elevated corridor from km 7.950 Uppal to km 14.200 of NH 163 to De-Congest the urban limits of Hyderabad-Bhoopalapatnam section on EPC mode in the state of Telangana — 75 months late
  13. Widening & strengthening of existing carriageway in 2 lane with paved shoulders from km 25/0 to 59/2 design Ch km 25.467 to 59.200 of NH - 353C on EPC mode in the state of Telangana — 74 months late
  14. Rehabilitation and upgradation of NH-167 from design km 113.900 to 154.479 Mallepally Haliya section to two lane with paved shoulders on EPC mode in the stte of Telangana — 73 months late
  15. Sri Ram Sagar Project Stage - II — 72 months late
  16. J. Chokka Rao Devadula Lift Irrigation Scheme — 72 months late
  17. Rehabilitation & upgradation of NH - 167 from design km 187.723 to 234.434 Miryalaguda to Kodad section to two lane with paved shoulder on EPC mode in the state of Telangana — 69 months late
  18. 6-laning of km 9.900 to km 19/948 Aramgarh to Shamshabad Section of Hyderabad Bangalore section of NH-44 Under NHO EPC basis in the state of Telangana — 67 months late
  19. Thanamcherla-Jamandlapally 2LPS — 39 months late
  20. Mobile connectivity in Left Wing Extremism [LWE] affected areas-Phase2 — 36 months late
  21. Construction of 4-lane flyover at Amberpet-X road, Hyderabad on NH-202 in the State of Telangana — 32 months late
  22. Kazipet Wagon Overhauling Project — 32 months late
  23. Jawahar Khani Open Cast Mine — 24 months late
  24. 4L of Kodad Design Km 0.00/Existing Km 185.00 of NH-65 to Khammam Design Km 31.800/Existing Km 29.400 of NH-365A — 24 months late
  25. Rehabilitation and Upgradation of LB-Nagar to Malkapur section to 6-Lane main carriageway with service roads, drains cum footpath, including VUPs and widening of Minor bridge & road safety provisions from Km. 15/00 to Km 40/00 of NH-65 Old NH-9 under NH O for the year 2020-21 in the state of Telangana on EPC Mode. — 23 months late