The public ticket board

Every central government infrastructure project (₹150 crore and above) as an open ticket — how long it has run, how late it is, what it costs now. Each ticket is automatically truth-checked by AI against live public reporting.

First time here? Beacon turns government project records into open tickets — delays, costs and AI truth-checks, all sourced. How this works →
Loading map…

Projects in Madhya Pradesh

123 open · 80 late · ₹318,695 crore. MP report cards in Madhya Pradesh.

  1. Indore - Gujarat / MP Border from km. Km 9.500 to Km 171.000 of NH-59 in MP — 159 months late
  2. Rehabilitation and upgradation Umaria to Shahdol section of NH-78 from Existing Km. 68/4 to Km. 142/2 to 2LPS including construction of Birshinghpur and Shahdol Bypass on EPC mode under NHDP-IVA — 107 months late
  3. Omkareshwar CADWM Project — 90 months late
  4. Bargi Diversion Project Phase - III [km. 104 to km 154] — 84 months late
  5. Bargi Diversion Project Phase - IV [km. 154 to km 197] — 75 months late
  6. Itarsi Km. 63.000 to Betul Km. 137.000 of NH-69 in Madhya Pradesh — 74 months late
  7. Indore Metro Rail Project — 73 months late
  8. Expansion of Malanjkhand Copper Project — 72 months late
  9. AMADAND OCP[4.0MTY] — 72 months late
  10. Bhopal Metro Rail Project — 67 months late
  11. Kandla Gorakhpur LPG Pipeline — 54 months late
  12. 502 Aspirational District Scheme in Four states - Bihar, Madhya Pradesh, Rajastha and Uttar Pradesh — 51 months late
  13. Jhansi - Bina Third Railway Line [153 Km] — 48 months late
  14. BLOCK B EXPANSION [3.5 TO 8.0 — 48 months late
  15. Jabalpur Sewerage Management and Treatment Infrastructure Project — 39 months late
  16. Indore Water Supply Infrastructure Project — 38 months late
  17. Singrauli Sewerage Management and Treatment Infrastructure Project — 38 months late
  18. Mumbai Nagpur Jharsuguda Pipeline Project — 37 months late
  19. BINA KAKRI AMALGAMATION EXPANS — 36 months late
  20. NIGAHI EXPANSION [15 TO 25 MTP — 36 months late
  21. Mobile connectivity in Left Wing Extremism [LWE] affected areas-Phase2 — 36 months late
  22. Dhangaon - Borgaon section km 81.000 to km 139.000 [Indore - Edlabad Pkg IV] — 33 months late
  23. Indore - Harda Pkg-III [Nanasa to Pidgaon Section from km 95.000 to km 142.445] — 30 months late
  24. Establishment of new GMC Rajgarh — 28 months late
  25. Satna Sewerage Management and Treatment Infrastructure Project — 26 months late