Every central government infrastructure project (₹150 crore and above) as an open ticket — how long it has run, how late it is, what it costs now. Each ticket is automatically truth-checked by AI against live public reporting.

First time here? Beacon turns government project records into open tickets — delays, costs and AI truth-checks, all sourced. How this works →
Loading map…

Projects in Karnataka

118 open · 86 late · ₹216,195 crore. MP report cards in Karnataka.

  1. Kochi - Koottanad - Bangalore - Mangalore Pipeline Phase-II — 165 months late
  2. Tumkur-Chitradurga — 150 months late
  3. Rayadurg-Tumkur via Kalyandurg New Line [207 km] — 149 months late
  4. Goa / Karnataka Km.93.700 to Kundapur Km.283.30 — 119 months late
  5. Multi Product Pipeline from Irugur to Devangonthi — 115 months late
  6. Tumkur-Chitradurga-Davangere New Rail Line Project [191 km] — 105 months late
  7. New Railway Line between Ginigera and Raichur [165.57 km] — 96 months late
  8. Hospet - Chitradurga from km. 299.00 to km. 418.750 — 94 months late
  9. Hassan km 184.912 to Maranahally km 230.060 of NH - 75 in Karnataka — 85 months late
  10. BRT Tiger Reserve Boundary Km.287.500 to Bangalore Section Km.458.420 of NH 209 in Karnataka — 81 months late
  11. Upper Tunga Irrigation Project — 75 months late
  12. 4L of Hubli - Hospet Section of NH-63 from Km 128.850 to Km 272.571 — 74 months late
  13. Davanagere - Haveri of NH-48 Old NH-4 from km. 260.00 to km. 338.923 — 74 months late
  14. Construction of Bangalore Metro Rail Project Phase 2. — 66 months late
  15. Belgaum-Khanapur Pkg I Km 0.000-Km 30.800 of NH-4A — 66 months late
  16. 4L Tumkur-Shimoga Pkg-I from Mallasandra to Karadi village of NH-206 from Km. 12.300 to Km. 65.195 — 54 months late
  17. 4L of Tumkur-Shimoga Pkg-II from Km 65.195 Karadi to Km 121.900 Banawara of NH-206 — 54 months late
  18. Bangalore-Nidagatta Pkg. I — 53 months late
  19. Construction of Major Bridge at Km.180.865 across river Krishna on NH 167 Hagari Jadcherla section — 52 months late
  20. Nidagatta-Mysore Pkg II — 46 months late
  21. Construction of Major Bridge Across Sharavathi Backwaters and approches between Ambargodu and Kalasavalli Near Sigandhur in Sagar Taluk on NH 369E in the State of Karnataka on EPC mode.Job No. NH-369E-KNT-2018-19-895 dated 06.03.2019. — 44 months late
  22. Belakeri Port to Kumta - Sirsi road from km 0.00 - km 4.265 of Belekeri Port Road Link Rd. and km 4.965 - km 60.00 of SH-69 — 41 months late
  23. 4L of Channarayapatna Bypass and Hassan Bypass with structures in Devihalli - Hassan section — 41 months late
  24. 4L of Bettadahalli- Shivamogga section from Km.170.415 to km. 226.750 of NH-206 Tumkur- Shivamogga Pkg-IV — 41 months late
  25. Hospet-Hubli-Vasco da Gama Line Electrification Project — 39 months late