Every central government infrastructure project (₹150 crore and above) as an open ticket — how long it has run, how late it is, what it costs now. Each ticket is automatically truth-checked by AI against live public reporting.

First time here? Beacon turns government project records into open tickets — delays, costs and AI truth-checks, all sourced. How this works →
Loading map…

Projects in Jharkhand

104 open · 60 late · ₹212,954 crore. MP report cards in Jharkhand.

  1. MURAIDIH UG PROJECT — 152 months late
  2. RAJRAPPA RCE OCP — 132 months late
  3. New Sinter Plant at BSL, SAIL — 116 months late
  4. Barwa Adda Km. 398.240 to Panagarh Km. 521.120 — 115 months late
  5. Master Plan for Jharia and Raniganj Coalfields — 112 months late
  6. 2.5 MTPA PATHERDIH NLW WASHERY — 104 months late
  7. MOONIDIH XV SEAM UG — 89 months late
  8. 4L/2L PS of Govindpur Raiganj - Chas - WB border section of from km. 0.00 to km. 56.889 of Old NH-32 — 80 months late
  9. Subernarekha Multipurpose Project, Jharkhand — 75 months late
  10. Six Laning of Bihar - Jharkhand Border Chordaha - Gorhar section of NH-2 from km 249.525 to km 320.810 — 61 months late
  11. North Koel Reservoir Project — 60 months late
  12. Patratu Thermal Power Station Expansion Project Phase-I [3x800 MW] — 47 months late
  13. 2L PS of JH / WB Border km. 70.524 - Purulia km.84.400 & Purulia km. 94.30 - Chandil Junction with NH-33 km. 153.705 of Old NH-32 — 46 months late
  14. Dhanbad Water Supply Infrastructure Project — 39 months late
  15. Augmentation and Strenghthning of Urban Water Supply Phase 1 - SAAP 3 — 39 months late
  16. Mobile connectivity in Left Wing Extremism [LWE] affected areas-Phase2 — 36 months late
  17. 4L of NH-80 from km 215.00 to km 260.00 Mirza Chauki to Farkka Pkg-I — 36 months late
  18. 4L from km 196.87 Sankha to km 219.6 Khajuri on NH-75 [Rehla / Garhwa Bypass] — 34 months late
  19. SAAP-3 Water Supply Infrastructure SAAP-3 Project — 32 months late
  20. Widening to 2-lane with paved shoulder from km 0.00 to 44.00 Kuru-Ghaghra section of NH-143A including re-construction of culverts and bridges. — 31 months late
  21. Provision of 4G based mobile services in 7,287 uncovered villages of 44 Aspirational District across 5 states of Andhra Pradesh, Chhattisgarh, Jharkhand, Maharashtra & Odisha — 30 months late
  22. New Delhi- Howrah Speed Booster[160Kmph] Project — 29 months late
  23. Development of Jharia CBM Block [Phase-1] — 28 months late
  24. Paradip-Numaligarh Crude Oil Pipeline [PNCPL] & Crude Oil Import Terminal [COIT] at Paradip — 27 months late
  25. 4L of Sahibganj - Manihari Ganga Bridge including Manihari Bypass — 26 months late