The public ticket board

Every central government infrastructure project (₹150 crore and above) as an open ticket — how long it has run, how late it is, what it costs now. Each ticket is automatically truth-checked by AI against live public reporting.

First time here? Beacon turns government project records into open tickets — delays, costs and AI truth-checks, all sourced. How this works →
Loading map…

Projects in Gujarat

122 open · 89 late · ₹523,895 crore. MP report cards in Gujarat.

  1. Ahmedabad Metro Rail Project [Phase-I] — 97 months late
  2. 6L of Chiloda-Naroda section from Km. 540.595 to Km. 555.595 of NH-8Package-VII — 84 months late
  3. 4L of Bhavnagar - Talaja Package-I from Km. 6.945 to Km. 54.990 of Old NH-8E — 84 months late
  4. Kagvadar - Una Package-IV — 79 months late
  5. Sardar Sarovar Project — 75 months late
  6. Sardar Sarovar CADWM Project — 75 months late
  7. Miyagam-Karjan-Dabhoi-Samlaya [GC] — 69 months late
  8. Kodinar - Veraval Package VI from km. 221.610 to km. 263.00 of NH-8E & km. 120.900 to km. 121.150 of NH-8D — 69 months late
  9. Four Laning of Una to Kodinar from km. 180.478 to km. 221.610 Package-V — 67 months late
  10. Pipli Bhavnagar-Package 1 from km 136.025 to km 169.328 — 59 months late
  11. Vadodara Mumbai Expressway Kim to Ankleshwar Phase IA - Pkg V — 56 months late
  12. Kandla Gorakhpur LPG Pipeline — 54 months late
  13. Rehablitation in Junavadaj Area Smart City Project — 49 months late
  14. 4L of Bal Works of Talaja - Mahuva from 54.990 km. to 100.450 km. of Old NH-8E Package-II — 47 months late
  15. Western Dedicated Freight Corridor — 45 months late
  16. 4L of Dwarka-Khambaliya-Devariya section from km 203.500 to km 176.500 and from km 171.800 to km 125.000 of NH-151A — 44 months late
  17. Bal. Works of Fagne Km. 510.000 to Maharashtra/Gujarat Border Km. 650.794 — 43 months late
  18. 4L of Bal Works of Mahuva to Kagvadar from 100.450 Km. to 140.470 Km. of NH-8E Pkg- III — 40 months late
  19. Upgradation of Sewerage system in Gandhinagar City — 38 months late
  20. Sanchore - Santalpur from km 99.000 - km 130.073 of NH-754K AJ-RGBS-Package-4 — 37 months late
  21. Delhi-Vadodara Greenfield Alignment NH-148N Pkg-31 Ch.824920 to Ch.844382 [Junction near Pratap nagar Village - Junction near Dodka Village] — 35 months late
  22. Transmission Network Expansion in Gujarat to increase its ATC from ISTS Part B — 35 months late
  23. Ahmedabad - Dholera Pkg III from km. 48.52 to km. 71.06 [Vejallka Village - Start of DSIR zone] — 33 months late
  24. Sanchore - Santalpur from km 67.000 - km 99.000 of NH-754K AJ-RGBS-Package-3 — 32 months late
  25. Vadodara Mumbai Expressway Talsari to Karvad Phase IB - Pkg X [Km 103.400 to Km 128.000] — 32 months late