The public ticket board

Every central government infrastructure project (₹150 crore and above) as an open ticket — how long it has run, how late it is, what it costs now. Each ticket is automatically truth-checked by AI against live public reporting.

First time here? Beacon turns government project records into open tickets — delays, costs and AI truth-checks, all sourced. How this works →
Loading map…

Projects in Delhi

23 open · 16 late · ₹128,249 crore. MP report cards in Delhi.

  1. Development of New Bijwasan Railway Terminal — 81 months late
  2. SETTING UP OF PHYSICAL INFRASTRUCTURE FOR THE NATIONAL INSTITUTE OF COMMUNICATION FINANCE [NICF] AT GHITORNI — 76 months late
  3. Dwarka Expressway Pkg-III Delhi/HR Border to Start of RoB Gurugram — 65 months late
  4. Anand Vihar-Tilak Bridge 3rd & 4th line — 57 months late
  5. 8L of Dwarka Expressway Pkg-II RuB near Dwarka Sector 21-DL/HR Border from 5.300 Km.to 9.500 Km. of NH-248BB — 54 months late
  6. Dwarka Expressway from Km -0.600 to Km 5.300 - Pkg-I Shivmurti Chowk-RuB near Dwarka Sector 21 — 43 months late
  7. Development of 6L UER II [Package - I] NH-1 Near Bakoli till Karala Kanjhawala Road from km. 0.70 to km.15.00 — 30 months late
  8. New Delhi- Howrah Speed Booster[160Kmph] Project — 29 months late
  9. Raising of speed to 160 kmph/200 kmph on existing New Delhi-Mumbai route incl. Vadodara-Ahmedabad — 24 months late
  10. DMRTS Phase - IV [3 Priority Corridors] — 21 months late
  11. 6L Access Controlled Highway from DND Maharani Bagh - Jn. with Jaitpur - Pushta Road of NH-148NA from km. 0.00 to km. 9.00 in NCR — 21 months late
  12. Transmission system for evacuation of power from REZ in Rajasthan 20GW under Phase-III Part J — 21 months late
  13. Akshardham - DL/UP Border Pkg-01 — 16 months late
  14. Transmission Scheme for Evacuation of power from REZ in Rajasthan [20 GW] under Phase-III Part D Phase I [Sikar Khetri Transmission Ltd] — 13 months late
  15. Redevelopment of Seven General Pool Residential Accommodation [GPRA] Colonies in Delhi — 8 months late
  16. Phase 1B - Construction of Academic Block, Hostel, Residential Tower, Directors Residence and External Development works at National Institute of Technology, Delhi Campus on Engineering, Procurement and Construction basis — 4 months late
  17. Setting up IT Infrastructure including Network Security and Hosting at AIIMS, New Delhi — -1 months late
  18. Delhi University Eastern Campus at Surajmal Vihar — -2 months late
  19. Redevelopment of Residential colonies at Ayur Vigyan Nagar and West Ansari Nagar campuses of AIIMS, New Delhi — -10 months late
  20. Redevelopment of New Delhi Railway Station and construction of associated infrastructure — -28 months late
  21. Delhi Metro Rail Phase V A — -28 months late
  22. Delhi Metro Rail Phase-IV [Rithala - Kundli Corridor] — -29 months late
  23. Delhi Metro Rail Phase-IV [2 Corridors] — -31 months late