The public ticket board

Every central government infrastructure project (₹150 crore and above) as an open ticket — how long it has run, how late it is, what it costs now. Each ticket is automatically truth-checked by AI against live public reporting.

First time here? Beacon turns government project records into open tickets — delays, costs and AI truth-checks, all sourced. How this works →
Loading map…

Projects in Chhattisgarh

78 open · 47 late · ₹155,651 crore. MP report cards in Chhattisgarh.

  1. 4/6 Laning of Raipur-Simga Pkg-I from km. 0.00 to km. 48.58 — 96 months late
  2. Kharsia-Dharamjaygarh with Spur line [East Corridor-Phase 1] — 90 months late
  3. Kelo Irrigation Project — 78 months late
  4. Doubling of Kirandul-Jagdalpur Line [150 km] — 74 months late
  5. Strengthening and widening of existing 2 lane road to two lane paved shoulder from km 7.750 to 26.542 & km. 32.093 to 45.786 of NH-130 on EPC mode in the state of chhattisgarh.job No. 130-CG-2017-18-348 — 63 months late
  6. Construction of 4 Nos Grade separtor between km. 281.000 to km. 307.600 km. 286.400 kumhari km. 299.000 Transport Nagar km. 302.000 Power House km. 304.000 Chandra Moura Chowk to km. 305.000 supeia of NH-53 old NH-06 Raipur - Durg 4 Lane on EPC mode in the state of chhattisgarh job NO. NH-53old NH-06 CG 2017-18-56 — 55 months late
  7. GEVRA OC [70 MTY] — 48 months late
  8. Gevra Road-Pendra Road New Railway Line [135 km] — 45 months late
  9. 4 Laning with PS of Pathrapalli-Katghora km 53.3 to km 92.6 Pkg-II of Bilaspur Kathghora — 42 months late
  10. Mumbai Nagpur Jharsuguda Pipeline Project — 37 months late
  11. Mobile connectivity in Left Wing Extremism [LWE] affected areas-Phase2 — 36 months late
  12. NMDC Slurry Pipeline Project Phase-1 — 34 months late
  13. Jagdalpur-Koraput — 33 months late
  14. Provision of 4G based mobile services in 7,287 uncovered villages of 44 Aspirational District across 5 states of Andhra Pradesh, Chhattisgarh, Jharkhand, Maharashtra & Odisha — 30 months late
  15. Up-gradation of NH-130C Abhanpur to Paund from NH Km. 0000 to KM 40380 to two lane with paved shoulders in the State of Chhattisgarh on EPC mode. — 29 months late
  16. 4L of Bilaspur to Urga km 0.00 to 70.2 of NH-130A — 28 months late
  17. 4 laning of Champa - Korba from km 0.00 to km 38.2 — 27 months late
  18. Development of 6L of Jhanki Sargi Section Road from km 0.000 to km 42.800 of NH 130CD Pkg-CG-1 — 27 months late
  19. Up-gradation of NH-930 Sherpar to Kohka from Km.67880 to Km.114860 to 2LPS in Chhattisgarh under EPC mode — 27 months late
  20. 6L of Dhanara - Hatibena Section from Km 124.611 to km 146.50 of NH-130-CD Package OD-1 — 25 months late
  21. Conversion of Partially Excavated Escape Tunnel to Uni-Directional 2L Tunnelincluding construction of cross passages and approach roads on either side of the tunnel from Km 12.732 to Km 14.568 of Kiratpur to Nerchowk Section of NH-21 — 25 months late
  22. JAGANNATHPUR OC RCE PROJECT — 24 months late
  23. MAHAMAYA OCP [1.50 MTY] — 24 months late
  24. Durg-Raipur-Arang Package - 2 from km. 44.50 to km. 92.23 near Khatti Village to near Aurang — 19 months late
  25. Rajnandgaon - Nagpur [Kalumna] Third Railway Line [228.30 km] — 18 months late