The public ticket board

Every central government infrastructure project (₹150 crore and above) as an open ticket — how long it has run, how late it is, what it costs now. Each ticket is automatically truth-checked by AI against live public reporting.

First time here? Beacon turns government project records into open tickets — delays, costs and AI truth-checks, all sourced. How this works →
Loading map…

Projects in Bihar

129 open · 101 late · ₹256,635 crore. MP report cards in Bihar.

  1. Chhapra - Hajipur from km. 143.200 to km. 209.200 — 153 months late
  2. Six Laning of Varanasi to Aurangabad from km. 786.00 to km. 978.40 of Old NH-2 — 147 months late
  3. Sitamarhi-Jaynagar Section km 79.400 to km 156.500 Lot-II — 89 months late
  4. Sheohar-Sitamarhi Section km 40.000 to 79.400 km Lot-I — 87 months late
  5. Simaria Km. 206.050 to Khagaria Km. 266.282 — 87 months late
  6. Hajipur-Sagauli New line — 81 months late
  7. Jaynagar-Narahia Section km 156.500 to km 219.945 Lot-III — 81 months late
  8. Gaya-Hisua-Rajgir-Nalanda-Biharsharif section km0.00 to 92.935 NH-82 — 80 months late
  9. Rehabilitation and Upgrading to 2 lanes/2-lane with paved shoulders configuration and strengthening of of Birpur and Bihpur Section from km 0.0 to Km 106 of NH 106 under phase I of National Highways Interconnectivity Improvement Projects NHIIP ICB No. NHIIP-BR-106-7 [NHIIP-BR-106-7] — 78 months late
  10. Bakhtiyarpur Km 153.300 to Mokama Km 197.900 — 76 months late
  11. Punpun Barrage Project — 75 months late
  12. Maheshkunt -Saharsa-Purnea Pkg II — 66 months late
  13. Six Laning of Bihar - Jharkhand Border Chordaha - Gorhar section of NH-2 from km 249.525 to km 320.810 — 61 months late
  14. North Koel Reservoir Project — 60 months late
  15. Construction of Approach Road to Rail-cum- Road Bridge across river Ganga at Munger Ghat NH-333 B — 59 months late
  16. Jogbani-Biratnagar New Rail Line project — 57 months late
  17. Maheshkunt-Saharsa-Purnea Pkg I km 0.00 to km. 90.00 of NH-107 — 55 months late
  18. 2L PS of Majhauli to Charout section from km. 0.00 to km. 63.655 — 53 months late
  19. 502 Aspirational District Scheme in Four states - Bihar, Madhya Pradesh, Rajastha and Uttar Pradesh — 51 months late
  20. Aunta - Simaria including Ganga Bridge — 50 months late
  21. Patna Metro Rail Project — 40 months late
  22. Barauni Refinery Capacity Expansion from 6.0 to 9.0 MMTPA — 40 months late
  23. Umagaon-Saharsa Package-IV Koshi Bridge & approach Road - Bheja-Bakaur — 37 months late
  24. Mobile connectivity in Left Wing Extremism [LWE] affected areas-Phase2 — 36 months late
  25. Balance work - WB-10 Gandak Bridge Km 402.00 to Km 440.00 Devanpur - Kotwa — 35 months late